Ohio
Mechanic's
Lien
Claims;
Pursuing
Claims
in Light
of Construction
Provisions
No lien contracts
An owner in Ohio may have a contract provision
providing that contractor may not file a lien on project.
The enforceability of such a provision is questionable. However,
some Ohio courts have upheld such "no lien" provisions
against contractors that sign them. Seveco, Inc. v. C&G
Investment Associates, 1977 LEXIS 7341 (Franklin Cty.
1977).
If a contractor agrees to a no lien provision,
the contractor must put the same language in any contracts
he enters into with lower tiered contractors or material suppliers.
In Pennsylvania, and in some other states,
no lien contracts have been sanctioned by the statute. The
no lien provision has to be filed with the county recorder's
office, to put all on notice.
Lien waivers
a. Partial lien waiver
Upon making progress payments, the owner or
general contractor will require the contractor to waive all
lien claims that the contractor may have for the work invoiced.
Such partial lien waiver requirement must be contained in
the contract. Partial lien waiver are often used in conjunction
with Affidavit of Contractor.
b. Final lien waiver
Upon completing the job, the contractor must
usually complete a final lien waiver.
The Fairness in Contracting Act states that
the requirement to sign a final waiver of claims in order
to obtain final payment is void and against public policy,
if the contractor has asserted a claim or request for an adjustment
to the contract price. Ohio Revised Code §4113.62(B). No longer
will contractors be caught between waiving a previously asserted
claim, and getting paid for its work.
c. Protecting lien rights in contract and
in waivers
Make sure lien waiver is contingent on payment,
either partial or final. Only waive liens through the date
of the invoice, not through the date of the payment.
Look for no lien clauses in your contract,
and in the contract with the owner, if that contract is incorporated
by reference. A no lien clause in the contract with the owner
may be incorporated into a lower tier contract, if there is
incorporation language in the lower tier contract. Such incorporation
language is usually enforced. If a no lien clause is in the
contract, try to negotiate it out of your contract.
Lien actions
a. Demand to file suit
Under the mechanic's lien law, an owner, or
another party on the owner's behalf, may demand that a lien
claimant commence foreclosure proceedings on a lien with 60
days of service of the demand. In order to accomplish such
a demand, the notice must be served on the lien claimant by
the county sheriff, and the notice must then be filed in the
county recorder's office within 30 days of service by the
sheriff. upon successful service, the lien claimant must then
commence foreclosure proceedings with 60 days of service,
or lose the right to do so. Ohio Revised Code §1311.11. Form
attached.
b. Where and when to file action for foreclosure
The foreclosure action must be filed in the
county where the property subject to the lien is located.
The action must be filed within six years of the date of the
filing of the lien.
c. What claims need to be brought?
The lien claimant should bring every cause
of action it has against the owner and the contractor that
the claimant contracted with in the same action. This is the
most efficient way to proceed, and the doctrine of res
judicata may prohibit the re-litigation of the issues
litigated in the foreclosure proceeding.
d. What must be proven to foreclose on
the lien?
In order to prevail, the lien claimant must
establish (a) the validity of the underlying contract claim,
(b) that the claim is within the mechanic's lien law, and
(c) that the claimant has taken all necessary steps to perfect
its lien.
e. Lien act damages
The remedy in a foreclosure action against
the owner is for the court to order the sale of the property,
and for the proceeds to be distributed to the lien claimant,
subject to the priority of any others holding a lien or security
interest in the property.
Lien claimants also have a right to attorneys
fees, to be paid from the funds generated by a sale of the
property.
Return
to Construction Law page
Fortney
& Klingshirn
4040 Embassy Parkway, Suite
280
Akron, Ohio 44333
telephone 330-665-5445 - fax 665-5446
|