Construction Claims Based on Contract
Claims against contracting party
A subcontractor or materialman may bring a
claim against the party it contracted with for breach of contract,
including claims based on refusal to pay the contract price,
refusal to pay for extra or changed work or materials, delay,
or violation of the prompt payment laws.
To prevail, the subcontractor or materialman
must establish the existence of a contract, performance of
the contract by the subcontractor or materialman, and breach
of the contract by the contracting party. Damages for breach
of contract are normally limited to the amount of money withheld.
For extra or changed work, the damages are the reasonable
value of the work performed. Damages under the prompt payment
law would also include interest and attorneys fees.
Claims against owner
Claims against the owner by a lower tier contractor
may be for foreclosure of mechanic's lien and for unjust enrichment.
Ohio courts have held that a claim for unjust
enrichment will be upheld where a benefit has been conferred
by a plaintiff on a defendant, the defendant has knowledge
of the benefit and the circumstances are such that it would
be unjust for the defendant to retain the benefit without
compensation. Hambleton v. R.G. Barry Corp. (1984),
12 Ohio St. 3d 179, 183, 465 N.E.2d 1298. Liability under
unjust enrichment "arises out of the obligation cast
by law upon a person in receipt of benefits which he is not
justly entitled to retain *** ." Hummel v. Hummel
(1938), 133 Ohio St. 520, 525.
Unjust enrichment claims against an owner
usually will not be upheld if the owner can demonstrate that
it paid for the work done or materials supplied, even if the
payment was not eventually made to the subcontractor or materialman.
Damages available
- Value of changed or additional work
- Money withheld
- Delay damages
Return
to Construction Law page
Fortney
& Klingshirn
4040 Embassy Parkway, Suite
280
Akron, Ohio 44333
telephone 330-665-5445 - fax 665-5446
|