'Pay When Paid' or 'Pay if Paid':
Contingent Payment Clauses
One of the greatest concerns
on a construction project is payment by the owner. Once the
contract work has been fully performed, everyone wants to
be, and should be, fully paid. One of the risks of nonpayment
is the owner's potential ability to pay. Contractors need
to agree on who bears the risk of nonpayment -- the general
contractor or the subcontractor.
Contractors routinely try to shift the burden
of nonpayment to its subcontractors. "Pay when paid"
and "pay if paid" provisions are popular. Courts
have held that most pay when paid clauses only serve to delay
the time for payment to the subcontractor, whereas a properly
worded pay if paid clause may actually shift the burden of
nonpayment to the subcontractor.
Typical pay when paid clauses provide something
like:
The total price paid to [subcontractor]
shall be [contract price], no part of which shall be paid
until 5 days after payment is received from owner.
or
. . . the Contractor shall pay the Subcontractor
each progress payment and final payment . . . within three
working days after he receives payment form the Owner .
. . .
The minority view; Mascioni v., L.B. Miller
Mascioni was
a 1933 New York case, where the court upheld a pay when paid
clause as being sufficient to shift the risk of non-payment
to the subcontractor. Some state courts have upheld the Mascioni
rule. Ohio courts have rejected Mascioni.
There is a limitation to Mascioni --
the reason for non-payment cannot be attributable to the actions
of the general contractor's failure to perform. If it is,
the subcontractor will be entitled to payment from the general
contractor.
The majority view; the Dyer interpretation
In Thos. J. Dyer v. Bishop International
Engineering Co., the Sixth Circuit U.S. Court of Appeals
refused to enforce a pay when paid clause. In Dyer,
a general contractor was not paid on a project after the owner
declared bankruptcy. The general contractor, in turn, did
not pay its subcontractor for the work it performed.
The Sixth Circuit held that conditions on
payment are enforceable, so long as such conditions are clearly
expressed. In construing the clause that "no part [of
payment] shall be due until five days after the owner shall
have paid the contractor", the court decided that the
clause was sufficiently ambiguous to require examination of
the parties' intent.
In examining the parties' intent, the court
noted that general contractors normally bear the risk of nonpayment
due to insolvency. The court held that this normal relationship
could be varied only with clear and unequivocal language.
Accordingly, the court held that the pay when
paid clause was only effective to delay payment "for
a reasonable period of time after the work was completed,
during which the general contractor would be afforded the
opportunity of procuring form the owner the funds necessary
to pay the subcontractor."
Ohio courts have followed the Dyer
rule. In Power & Pollution Services, Inc. v. Suburban
Power Piping Corp., the Cuyahoga County Court of Appeals
reversed the trial court's dismissal of a subcontractor's
claim against a general contractor after the owner, LTV Steel,
declared bankruptcy. The subcontract contained the language
that the general contractor "shall not be required to
pay such monthly billing of the subcontractor prior to the
date Company receives payment of its corresponding monthly
billing from the Owner."
"Pay if paid"; satisfying the Dyer
concerns
How do contractors shift the burden of nonpayment
by the owner? Say it clearly in a contract provision.
What should be said? The contract should state
that
- the subcontractor is paid only if
the general contractor is paid, (or the subcontractor will
not be paid unless the general contractor receives payment
from the owner); and
- the subcontractor assumes the risk of
nonpayment by the owner due to insolvency or other inability
to pay.
Such contract language has been held by many
courts to sufficiently shift the burden of nonpayment to the
subcontractor.
Some states, however, have held that such
risk shifting violates public policy. The California Supreme
Court has ruled "pay if paid" clauses are unenforceable
as a violation of California’s public policy. Wm. R. Clarke
Corp. v. Safeco Ins. Co. of Amer., 938 P.2d 372 (Cal.
1997). The court noted that a "pay if paid" clause
is an indirect forfeiture of a subcontractor’s constitutionally
protected lien rights. The New York high court has likewise
concluded that "pay if paid" clauses are void as
against public policy.
Return
to Construction Law page
Fortney
& Klingshirn
4040 Embassy Parkway, Suite
280
Akron, Ohio 44333
telephone 330-665-5445 - fax 665-5446
|