No lien contracts
An owner in Ohio may have a contract provision providing that contractor may not file a
lien on project. The enforceability of such a provision is questionable. However, some
Ohio courts have upheld such "no lien" provisions against contractors that sign
them. Seveco, Inc. v. C&G Investment Associates, 1977 LEXIS 7341 (Franklin Cty.
1977).
If a contractor agrees to a no lien provision, the contractor must put the same
language in any contracts he enters into with lower tiered contractors or material
suppliers.
In Pennsylvania, and in some other states, no lien contracts have been sanctioned by
the statute. The no lien provision has to be filed with the county recorder's office, to
put all on notice.
Lien waivers
a. Partial lien waiver
Upon making progress payments, the owner or general contractor will require the
contractor to waive all lien claims that the contractor may have for the work invoiced.
Such partial lien waiver requirement must be contained in the contract. Partial lien
waiver are often used in conjunction with Affidavit of Contractor.
b. Final lien waiver
Upon completing the job, the contractor must usually complete a final lien waiver.
The Fairness in Contracting Act states that the requirement to sign a final waiver of
claims in order to obtain final payment is void and against public policy, if the
contractor has asserted a claim or request for an adjustment to the contract price. Ohio
Revised Code §4113.62(B). No longer will contractors be caught between waiving a
previously asserted claim, and getting paid for its work.
- Protecting lien rights in contract and in waivers
Make sure lien waiver is contingent on payment, either partial or final. Only waive
liens through the date of the invoice, not through the date of the payment.
Look for no lien clauses in your contract, and in the contract with the owner, if that
contract is incorporated by reference. A no lien clause in the contract with the owner may
be incorporated into a lower tier contract, if there is incorporation language in the
lower tier contract. Such incorporation language is usually enforced. If a no lien clause
is in the contract, try to negotiate it out of your contract.
Lien actions
- Demand to file suit
Under the mechanic's lien law, an owner, or another party on the owner's behalf, may
demand that a lien claimant commence foreclosure proceedings on a lien with 60 days of
service of the demand. In order to accomplish such a demand, the notice must be served on
the lien claimant by the county sheriff, and the notice must then be filed in the county
recorder's office within 30 days of service by the sheriff. upon successful service, the
lien claimant must then commence foreclosure proceedings with 60 days of service, or lose
the right to do so. Ohio Revised Code §1311.11. Form attached.
- Where and when to file action for foreclosure
The foreclosure action must be filed in the county where the property subject to the
lien is located. The action must be filed within six years of the date of the filing of
the lien.
- What claims need to be brought?
The lien claimant should bring every cause of action it has against the owner and the
contractor that the claimant contracted with in the same action. This is the most
efficient way to proceed, and the doctrine of res judicata may prohibit the
re-litigation of the issues litigated in the foreclosure proceeding.
- What must be proven to foreclose on the lien?
In order to prevail, the lien claimant must establish (a) the validity of the
underlying contract claim, (b) that the claim is within the mechanic's lien law, and (c)
that the claimant has taken all necessary steps to perfect its lien.
- Lien act damages
The remedy in a foreclosure action against the owner is for the court to order the sale
of the property, and for the proceeds to be distributed to the lien claimant, subject to
the priority of any others holding a lien or security interest in the property.
Lien claimants also have a right to attorneys fees, to be paid from the funds generated
by a sale of the property.
Return
to Construction Law page
4040 Embassy Parkway Suite 280
Akron, Ohio 44333
330-665-5445 fax 330- 665-5446
This site was last
updated on November 02, 2006 |