Scope of work in contractDisputes regarding scope of work are often the reason for
construction claims. Scope of work is defined as the extent of a contractor's
responsibility to perform certain contract work. To determine the scope of work, the
contractor may have to look to other contract documents -- specifications, contracts with
others -- and to industry standards (building codes, etc.).
Questions regarding scope of work should be resolved in the written contract. Scope of
work references should be detailed in contract. If detailed specifications are available,
refer to the specifications in designating scope of work.
Changed or extra work contract procedure
The changed work provision is a mechanism to allow the owner to demand changes without
requiring negotiated agreement with contractor. Unilateral changes may entitle the
contractor to additional money and time to complete. Reasons for changes may be to correct
errors and/or omissions in plans and specifications, to satisfy regulatory agencies, to
effect minor design changes, to address quantities of materials used, and to extend time
for completion of the contract.
The changes clause should address the scope of the changed work, the contract
adjustment in price, and the procedure to be followed. Under the typical changed work
provision, the owner may direct changes and the contractor must perform changes even if
there is no agreement as to price.
Extra work is work not contemplated by contract -- changed work is work contemplated by
contract but where the scope of the work has changed.
Preserving claims for failure to pay for extra work
- Invoicing/waivers
Application for payment includes (a) value of work in place, (b) value of materials
stored on site, (c) retainage, (d) amounts previously paid, and (e) amount due for present
request. The invoice form should specifically refer to the project, the contract, and the
contract sum.
1. Determining value of work in place
A properly and carefully prepared schedule of values, and good record keeping by the
contractor, assist the determination of the value of work in place. The contractor should
keep meticulous records of payroll, supplies, equipment, materials, and overhead to
present in the event of a dispute.
The contractor may be required to submit breakdown of hours, position, and wage rates
of employees on project. Overtime hours and the reason for overtime should also be
tracked. The contractor should be able to show the cost of labor incurred for each
component of work completed.
The cost of supplies should be separately tracked. Supplies are not incorporated in
project, as materials are. Equipment rental and/or maintenance should be tracked along
with supplies.
Materials used must also be tracked as part of the value of the work in place.
Materials are those that have been incorporated into the project.
Overhead and profit should also be part of the value of work in place. Appropriate
amount should be added to value.
2.. Determining cost of material stored on site
This component of application for payment is the material stored on site, but not yet
incorporated into the project. This allows the contractor to purchase materials before
they are needed, so as to allow construction to proceed without delay.
3. Retainage
Usually spelled out in contract. If it is not, retainage is not an automatic right.
- Schedule of values
A schedule of values is typically required by contract documents. The schedule should
be prepared carefully, with specific and accurate values attached to each component of the
work. The schedule should be submitted prior to the first application for payment, and
should be reviewed carefully by architect to prevent "front end loading" by
contractor.
Return
to Construction Law page
4040 Embassy Parkway Suite 280
Akron, Ohio 44333
330-665-5445 fax 330- 665-5446
This site was last
updated on November 02, 2006 |