Claims against contracting partyA subcontractor or materialman may bring a claim
against the party it contracted with for breach of contract, including claims based on
refusal to pay the contract price, refusal to pay for extra or changed work or materials,
delay, or violation of the prompt payment laws.
To prevail, the subcontractor or materialman must establish the existence of a
contract, performance of the contract by the subcontractor or materialman, and breach of
the contract by the contracting party. Damages for breach of contract are normally limited
to the amount of money withheld. For extra or changed work, the damages are the reasonable
value of the work performed. Damages under the prompt payment law would also include
interest and attorneys fees.
Claims against owner
Claims against the owner by a lower tier contractor may be for foreclosure of
mechanic's lien and for unjust enrichment.
Ohio courts have held that a claim for unjust enrichment will be upheld where a benefit
has been conferred by a plaintiff on a defendant, the defendant has knowledge of the
benefit and the circumstances are such that it would be unjust for the defendant to retain
the benefit without compensation. Hambleton v. R.G. Barry Corp. (1984), 12 Ohio St.
3d 179, 183, 465 N.E.2d 1298. Liability under unjust enrichment "arises out of the
obligation cast by law upon a person in receipt of benefits which he is not justly
entitled to retain *** ." Hummel v. Hummel (1938), 133 Ohio St. 520, 525.
Unjust enrichment claims against an owner usually will not be upheld if the owner can
demonstrate that it paid for the work done or materials supplied, even if the payment was
not eventually made to the subcontractor or materialman.
Damages available
- Value of changed or additional work
- Money withheld
- Delay damages
Return
to Construction Law page
4040 Embassy Parkway Suite 280
Akron, Ohio 44333
330-665-5445 fax 330- 665-5446
This site was last
updated on November 02, 2006 |